Back to all reports

75' of footpath was prepared for resurfacing - but not completed.

Reported in the Footway or Footpath category by Mike WARRINGTON at 12:42, Tuesday 8 January 2019

Sent to Rutland County Council 3 minutes later

An area at the junction of Aveland Road and Spinney Road was prepared for resurfacing during 2018 but was not completed. Large cracks and a pothole was exposed and still remain. This work could be completed when footpath works are undertaken during January on Park Road.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review. We will investigate this and respond to you within 10 working days. Updates will be posted on FixMyStreet. IMPORTANT: To report anything dangerous, please call us on: 01572 722577. Regards Rutland Highways

    Posted by highways at 13:50, Tuesday 8 January 2019

  • Pothole &n crack filled - but no resurfacing

    State changed to: Fixed

    Posted by Mike WARRINGTON at 13:54, Tuesday 5 February 2019

  • Works to be programmed for NFY. Safety defects made safe in meantime.

    Posted by RCC at 12:07, Wednesday 6 February 2019

This report is now closed to updates. You can make a new report in the same location.